CONSTRUCTION UPDATE NOTICE 

 

Weeks of: April 7, 2014 and April 14, 2014 

 

What to Expect On-Site the Next Two Weeks: 

During the next two weeks of construction, the General Contractor, L.F.
Jennings, will continue installing erosion and sediment control fencing and
ponds, installing perimeter fencing, continue site clearing on the west end
of the site, continue removal and haul-off of excess soil and begin the
rough grading on the west end of the site. 

 

These activities will require heavy equipment accessing the site. Two
construction entrances are located along Route 1 located near both ends of
the project site and one entrance at Maryland Avenue. 

 

Lane Closures: 

There are no anticipated lane closures associated with this work. 

 

Construction Hours: 

Construction activity will be taking place Monday - Saturday between the
hours of 7 a.m. and 5 p.m. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20140407/89dc748f/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 14NOTICE-MARCH Cafritz Project Construction Update Weeks of 4-7 and 4-14-14.pdf
Type: application/pdf
Size: 13180 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20140407/89dc748f/attachment.pdf>


More information about the TownAnnounce mailing list