[RP Town Announce] Cafritz Construction Update Notice for Weeks of: May 19, 2014 and May 26, 2014

Jessica Barnes jbarnes at riverdaleparkmd.gov
Wed May 21 14:16:04 UTC 2014


CALVIN CAFRITZ ENTERPRISES 

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: May 19, 2014 and May 26, 2014 

 

What to Expect On-Site the Next Two Weeks: 

During the next two weeks of construction, the General Contractor, L.F.
Jennings, will continue clearing the site, continue removal and haul-off of
excess soil and trees, and continue rough grading operations on the west
side of the site, utilizing both material haul-off as well as on-site cut to
fill. 

These activities will require heavy equipment accessing the site. Two of the
construction entrances are located along Route 1 located near both ends of
the project site and one entrance at Maryland Avenue. 

 

Lane Closures: 

There are no anticipated lane closures associated with this work. 

 

Construction Hours: 

Construction activity will be taking place Monday - Saturday between the
hours of 7 a.m. and 5 p.m. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital

 

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20140521/b46be8da/attachment.html>


More information about the TownAnnounce mailing list