[RP Town Announce] Riverdale Park Station - Construction Update Notice for the Weeks of August 31 and September 7, 2015
Jessica Barnes
jbarnes at riverdaleparkmd.gov
Fri Aug 28 19:37:10 UTC 2015
Riverdale Park Station
CONSTRUCTION UPDATE NOTICE
Weeks of: August 31, 2015 and September 7, 2015
What to Expect On-Site the Next Two Weeks:
During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market and Building #3.
Underground utility work to install storm drains and sewers is proceeding in
multiple areas on the site. Electrical conduits are complete from Route1 to
Whole Foods Market. Pepco crews are currently installing cabling and
equipment for permanent power on site. The sanitary sewer work is ongoing
and will continue. The storm drain installation around the Whole Foods
Market has begun.
Lane Closures:
New storm water outfall line under Route 1 has been installed. Other utility
connections for sanitary sewer, water, Verizon, Comcast and gas will now
commence.
Future Plans:
. Two week to two month look-ahead -
o Continue all of the above work but start an additional building to provide
new retail to the area.
o Start construction of the Whole Foods Market parking lot.
o Start construction of the pond at the northeast corner of the site.
o Start utility relocation for the construction of the CSX Crossing east of
the railroad tracks.
o Begin widening of Route 1, installation of curb & gutter, and construction
of on-site roads.
o Start installation of a traffic signal at Van Buren St. & Route1.
o Begin construction of miscellaneous site structures in Gateway Park.
o WGL to begin relocation of existing gas main in Maryland Ave. followed by
installation of new storm drain outfall to Wells Run box culvert.
. Two to six month look-ahead -
o Start additional retail buildings.
o Start interior fit-out of Whole Foods.
o Finish widening of Route 1.
o Opening of Gateway Park.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00 a.m. to 3:00 p.m.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20150828/6b08bfeb/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 8-31-15 and 9-7-15 FINAL.pdf
Type: application/pdf
Size: 30486 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20150828/6b08bfeb/attachment.pdf>
More information about the TownAnnounce
mailing list