[RP Town Announce] Riverdale Park Station Construction Update Notice for Weeks of: December 14, 2015 thru the week of December 28, 2015

Jessica Barnes jbarnes at riverdaleparkmd.gov
Sat Dec 12 14:38:38 UTC 2015


Riverdale Park Station

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: December 14, 2015 thru the week of December 28, 2015 

 

What to Expect On-Site the Next Three Weeks: 

During the next three weeks of work, the General Contractor, L.F. Jennings,
and their subcontractors will continue site construction around the Whole
Foods Market and along Route 1. Underground utility work to install storm
drains, water mains, conduits, site lighting and sanitary sewers is
proceeding in multiple areas on the site. Washington Gas continues to bring
gas lines to each new building. 

 

Grading for the pervious pavement drainage system, under the Whole Foods
parking lot, will continue. The installation of the asphalt base course for
the widening of Route 1 is complete. Underground conduit installation for
the new traffic signal at Van Buren St. and Route 1 is ongoing. Construction
of the three new entrances from Route 1 into the development has been
completed. Curb & gutter and base asphalt paving of the roads around the
Whole Food Market is underway. 

 

Construction of screen walls, seat walls, sign walls and other site
hardscape structures in Gateway Park (buffer area adjacent to Route 1) and
around the Whole Foods Market parking lot has begun. 

 

The construction of a large permanent storm water management pond in the NE
corner of the site will begin soon. Washington Gas Light ("WGL") is
relocating a gas line running along Rhode Island Ave. to the west of the
railroad tracks that will impact traffic from Wells Run to the Pittcon
facility. This project should be completed by 12/24/15. Once the WGL work is
done, the installation of a new storm drain outfall pipe will begin from
Wells Run to the the site. 

 

CSX Crossing: 

Work will soon begin on the much awaited new CSX crossing at Riverdale Park
Station. The bridge construction work is significant and requires the
closing of the former ERCO plant parking lot between the Rivertech Court
cul-de-sac and Lafayette Avenue. This route has been used for years as a
"short cut" from Lafayette Avenue to M-Square. The closure will begin on or
about December 14, 2015 and will continue until the new bridge is open -
estimated to be in April 2017. 

 

The initial construction activities include the relocation of existing
electrical and gas utilities that run parallel to the CSX tracks. Utility
relocations are necessary for the construction of the new bridge over the
CSX railroad tracks. 

Temporary detour signage will be installed at the point of the construction
directing bicyclists to an alternate route around the bridge construction.
In addition, Gateway Park along the Route 1 frontage of the site will soon
be open and provide bike/pedestrian access along Route 1. 

 

Lane Closures: 

Utility connections for traffic signalization conduits are being performed
that require periodic lane closures in Route 1. All utility work in Route 1
will be complete by 12/18/15.

 

Future Plans: 

. Two week to two month look-ahead - 

o Continue all of the above work but start additional buildings to provide
new retail to the area. 

o Start utility relocation for the construction of the CSX Crossing east of
the railroad tracks. 

o Opening of Gateway Park. 

 

. Two to six month look-ahead - 

o Start additional retail buildings. 

o Start interior fit-out of Whole Foods. 

 

Work Hours: 

Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00 a.m. to 3:00 p.m. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction

 

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20151212/0eb8ee10/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 12-14-15 thru week of 12-28-15 FINAL.pdf
Type: application/pdf
Size: 31091 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20151212/0eb8ee10/attachment.pdf>


More information about the TownAnnounce mailing list