[RP Town Announce] Riverdale Park Station - Construction Update Notice Weeks of: May 25, 2015 and June 1, 2015

Jessica Barnes jbarnes at riverdaleparkmd.gov
Tue May 26 13:36:57 UTC 2015


Riverdale Park Station

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: May 25, 2015 and June 1, 2015 

 

What to Expect On-Site the Next Two Weeks: 

During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market and Building #3. 

 

Lane Closures: 

WSSC has commenced work on their replacement water main project in the Route
1 right-of-way. This work is not associated with the Riverdale Park Station
project. 

 

It is anticipated that work will begin in the next few weeks on installing
the storm drain pipe in Route 1. As well, it is anticipated that Pepco will
be installing a new pole and underground electric conduits across Route 1. 

 

Future Plans: 

. Two week to two month look-ahead - 

o Continue all of the above work but start an additional building to provide
new retail to the area. 

o Utility installation work. 

o Start construction of the Whole Foods Market parking lot. 

o Start construction of the pond at the northeast corner of the site. 

o Start utility relocation for the construction of the CSX Crossing. 

 

. Two to six month look-ahead - 

o Start additional retail buildings. 

o Start installation of a traffic signal at Van Buren St. & Rt.1. 

 

. Six to twelve month look-ahead - 

o Start interior fit-out of Whole Foods. 

o Finish widening of Route 1. 

o Opening of Gateway Park. 

 

Work Hours: 

Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00 a.m. to 3:00 p.m. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.

 

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20150526/16f81761/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 5-25-15 and 6-1-15 FINAL.pdf
Type: application/pdf
Size: 29618 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20150526/16f81761/attachment.pdf>


More information about the TownAnnounce mailing list