[RP Town Announce] Riverdale Park Station: Construction Update Notice for the weeks of August 29 and September 5, 2016
Jessica Barnes
jbarnes at riverdaleparkmd.gov
Mon Aug 29 17:48:58 UTC 2016
Riverdale Park Station
CONSTRUCTION UPDATE NOTICE
Weeks of: August 29, 2016 thru the week of September 5, 2016
What to Expect On-Site the Next Two Weeks:
The General Contractor, L.F. Jennings, will continue site construction in
multiple areas on the site. Washington Gas Light (WGL), Verizon, Comcast,
WSSC and Pepco will bring utility services to each new building.
New road construction east of 46th Street to connect to Maryland Avenue is
ongoing. The final asphalt topping course and striping of roads and parking
areas will be completed before the end of the year on the western half of
the site. The park adjacent to Route 1 (Gateway Park) is nearing completion.
Bio-soil storm water retention devices are being installed throughout the
site. The sidewalk and road work along Maryland Avenue, at the southeast
corner of the site, has started.
Fine grading for 119 townhome lots is ongoing so the townhome builder can
start construction of these units this fall. Conduit and/or pipe
installation for Washington Gas Light (WGL), Verizon, Comcast and Pepco
services to each townhouse lot is ongoing. The first lots are being turned
over to the townhouse developer in September.
Construction of three new commercial buildings (#1, 2 & 4) is well underway.
Tenant fitout work in Building #3, for spaces other than Whole Foods Market,
has started.
CSX Crossing:
The bridge construction requires the closing of the former ERCO plant
parking lot between the Rivertech Court cul-de-sac and Lafayette Avenue.
This route has been used for years as a "short cut" from Lafayette Avenue to
M-Square. This closure will continue until the new bridge is open -
estimated to be in the third quarter of 2017. Initial activities will
include driving of piles for the bridge foundation. This pile driving will
generate noise around that area. The pile installation should start in
September.
Whole Foods Market:
Tenant fitout work inside Whole Foods Market has started. This construction
is being managed by Whole Foods Market. They estimate that construction,
stocking and employee training will take 9-10 months from the time
construction work commences.
Hiker/Biker Trail:
The Hiker/Biker Trail has been deeded to MNCPPC's Department of Parks and
Recreation who will manage and maintain the trail. They expect to open the
trail for use by the public once they determine that site conditions are
suitably safe from dangers associated with the immediately adjacent
construction activities.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway (Route 1) will be
restricted to 9:00 a.m. to 3:00 p.m.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants, Inc. at 202-669-7157 or email at
rlockhart at ccci-dc.com.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20160829/b6781eaa/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 8-29-16 thru week of 9-5-16 FINAL.pdf
Type: application/pdf
Size: 87404 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20160829/b6781eaa/attachment.pdf>