[RP Town Announce] Riverdale Park Station - Construction Update Notice Weeks of March 28 and April 4, 2016

Jessica Barnes jbarnes at riverdaleparkmd.gov
Mon Mar 28 15:11:08 UTC 2016


Riverdale Park Station

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: March 28, 2016 thru the week of April 4, 2016 

 

What to Expect On-Site the Next Two Weeks: 

During the next two weeks the General Contractor, L.F. Jennings, will
continue site construction including underground utility work to install
storm drains, water mains, electric conduits and site lighting in multiple
areas on the site. Washington Gas Light (WGL) and PEPCO continue to bring
service to each new building. 

 

Installation of curb and gutter around the entire east side of the site is
ongoing. Installation of the new traffic signal at Van Buren Street and
Route 1 is complete. This signal will be the property of the State and will
most likely be placed into operation just prior to Riverdale Park Station
opening. The parking lot in front of the Whole Foods Market will be paved
and the first course of paving around the Whole Foods Market will be placed.
The final asphalt top course and striping will be completed later this
spring. 

 

Construction of screen walls, seat walls, sign walls and other site
hardscape structures in Gateway Park (buffer area adjacent to Route 1) and
around the Whole Foods Market parking lot is ongoing. Final grading of the
dirt in this buffer area is ongoing in preparation for landscape plantings.
Bio-soil storm water retention devices are being installed throughout the
site as required. 

 

The construction of a large permanent storm water management pond in the NE
corner of the site and the installation of a new storm drain outfall pipe
under Rhode Island Avenue, from Wells Run to the site, is ongoing. 

 

CSX Crossing: 

Work has started on the much awaited new CSX crossing at Riverdale Park
Station. The bridge construction work is significant and required the
closing of the former ERCO plant parking lot between the Rivertech Court
cul-de-sac and Lafayette Avenue. While this route has been used for years as
a "short cut" from Lafayette Avenue to M-Square, some vehicles are going
around the barriers only to find parts of the road removed. As a reminder,
all vehicles should honor the signs noting closure of the road. This closure
will continue until the new bridge is open - estimated to be in April 2017. 

 

The initial construction activities include the relocation of existing
electrical, communication and gas utilities that run parallel to the CSX
tracks. The gas line relocation has started. Utility relocations are
necessary for the construction of the new bridge over the CSX railroad
tracks. 

 

Lane Closures: 

Periodic lane closures along Route 1 may be required but long term closures
are not scheduled. 

 

Future Plans: 

. Two week to two month look-ahead - 

o Continue all of the above work but start additional buildings to provide
new retail businesses to the area.

o Perform spring landscaping for areas completed during winter months. 

o Opening of Gateway Park buffer area along Rt. 1. 

 

. Two to six month look-ahead - 

o Start a residential/parking building. 

o Start interior fit-out of Whole Foods. 

 

Work Hours: 

Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway (Route 1) will be
restricted to 9:00 a.m. to 3:00 p.m.

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants, Inc. at 202-669-7157 or email at
rlockhart at ccci-dc.com.

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20160328/61315a65/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 3-28-16 thru week  of  4-4-16 FINAL.pdf
Type: application/pdf
Size: 30238 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/townannounce/attachments/20160328/61315a65/attachment.pdf>


More information about the TownAnnounce mailing list