 I know someone had asked about getting mulch from the construction site. See response below.


Valrie 
 
 
 
On Tuesday, April 8, 2014 7:16 AM, Robert Lockhart <rlockhart at ccci-dc.com> wrote:
  
Ms. Hames, 
Please let the residents know that the suitable topsoil is being stored on site and will be spread after the new buildings are in place to create landscaped areas to be enjoyed by everyone.  Trees  are being removed from the site and are not mulched.  Small shrubs, that are being mulched, produce a product that is not suitable for residential use.  If things change, I will get back to you. 
  
Robert M. Lockhart 
Robert M. Lockhart 
Executive Vice President 
Capital Construction Consultants 
1120 Connecticut Ave., NW   Suite 1050 
Washington, DC  20036 
Tel. 202.669.7157  
  
From:Valrie Hames [mailto:crownvhg at yahoo.com] 
Sent: Monday, April 07, 2014 9:19 PM
To: Robert Lockhart
Subject: Re: [RP TownTalk] Cafritz Project Construction Update Weeks of 4/7 and 4/14   
  
Hello Mr. Lockhart,  
   
Some of the residents of Riverdale Park would like to know if there are any soil or tree mulch that residents can put to use at their gardens?

   
Valrie Hames  
Riverdale Park Resident  
   
   
   
     
On Monday, April 7, 2014 7:07 PM, Jessica Barnes <jbarnes at riverdaleparkmd.gov> wrote:  
CONSTRUCTION UPDATE NOTICE   
   
Weeks of: April 7, 2014 and April 14, 2014   
   
What to Expect On-Site the Next Two Weeks:   
During the next two weeks of construction, the General Contractor, L.F. Jennings, will continue installing erosion and sediment control fencing and ponds, installing perimeter fencing, continue site clearing on the west end of the site, continue removal and haul-off of excess soil and begin the rough grading on the west end of the site.   
   
These activities will require heavy equipment accessing the site. Two construction entrances are located along Route 1 located near both ends of the project site and one entrance at Maryland Avenue.   
   
Lane Closures:   
There are no anticipated lane closures associated with this work.   
   
Construction Hours:   
Construction activity will be taking place Monday – Saturday between the hours of 7 a.m. and 5 p.m.   
   
Contact Information:   
For any construction related concerns, please contact Robert Lockhart of Capital Construction Consultants at 202-669-7157 or email at rlockhart at ccci-dc.com.  
   
Jessica  
Jessica E. Barnes  
Town Clerk  
Riverdale Park  
5008 Queensbury Road  
Riverdale Park, MD 20737  
http://www.riverdaleparkmd.info/  
301-927-6381  
      

_______________________________________________
TownTalk mailing list
To post to the list, send mail to TownTalk at riverdale-park.org
TownTalk-request at riverdale-park.org is for automated subscription processing only
http://riverdale-park.org/mailman/listinfo/towntalk

For more information about Riverdale Park, visit http://www.riverdaleparkmd.info/
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20140409/1cb6c0cc/attachment.html>


More information about the TownTalk mailing list