[RP TownTalk] Cafritz Construction Update Notice for Weeks of July 14, 2014 and July 21, 2014

Jessica Barnes jbarnes at riverdaleparkmd.gov
Mon Jul 14 12:34:42 UTC 2014


CALVIN CAFRITZ ENTERPRISES 

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: July 14, 2014 and July 21, 2014 

 

What to Expect On-Site the Next Two Weeks: 

During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue clearing the site, continue removal and haul-off of excess
soil and trees, and continue rough grading operations on the site, utilizing
both material haul-off as well as on-site cut to fill. This will include
work along the Route 1 buffer area. 

 

These activities will require heavy equipment accessing the site. Two of the
construction entrances are located along Route 1 located near both ends of
the project site and one entrance at Maryland Avenue. 

 

Lane Closures: 

There are no anticipated lane closures associated with this work. 

 

Work Hours: 

Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 5 p.m. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.

 

 

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20140714/9bcebf3e/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 7-14 and 7-21-14.pdf
Type: application/pdf
Size: 13087 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20140714/9bcebf3e/attachment.pdf>


More information about the TownTalk mailing list