CALVIN CAFRITZ ENTERPRISES
CONSTRUCTION UPDATE NOTICE
Weeks of: June 2, 2014 and June 9, 2014
What to Expect On-Site the Next Two Weeks:
During the next two weeks of construction, the General Contractor, L.F.
Jennings, will continue clearing the site, continue removal and haul-off of
excess soil and trees, and continue rough grading operations on the site,
utilizing both material haul-off as well as on-site cut to fill.
These activities will require heavy equipment accessing the site. Two of the
construction entrances are located along Route 1 located near both ends of
the project site and one entrance at Maryland Avenue.
Lane Closures:
There are no anticipated lane closures associated with this work.
Construction Hours:
Construction activity will be taking place Monday - Saturday between the
hours of 7 a.m. and 5 p.m.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20140602/94f978fd/attachment.html>
More information about the TownTalk
mailing list