[RP TownTalk] Riverdale Park Station - Construction Update Notice Weeks of: April 27, 2015 and May 4, 2015

Jessica Barnes jbarnes at riverdaleparkmd.gov
Fri Apr 24 17:03:01 UTC 2015


Riverdale Park Station

CONSTRUCTION UPDATE NOTICE 

 

Weeks of: April 27, 2015 and May 4, 2015

What to Expect On-Site the Next Two Weeks: 

During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market. They will also
continue removal and haul-off of excess soil and rubble. 

 

The installation of the retaining wall along the Northern property line will
be completed by the end of April. 

 

Lane Closures: 

WSSC has commenced work on their replacement water main project in the Route
1 right-of-way. This work is not associated with the Riverdale Park Station
project. 

 

Future Plans: 

. Two week to two month look-ahead - 

o Continue all of the above work but start an additional building to provide
new retail to the area. 

o Utility installation work. 

o Start construction of the pond at the northeast corner of the site. 

o Start utility relocation for the construction of the CSX Crossing. 

 

. Two to six month look-ahead - 

o Start additional retail buildings. 

o Start installation of a traffic signal at Van Buren St. & Rt.1. 

 

. Six to twelve month look-ahead - 

o Start interior fit-out of Whole Foods. 

o Finish widening of Route 1. 

o Opening of Gateway Park. 

 

Work Hours: 

Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00am to 3:00pm. 

 

Contact Information: 

For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.

 

 

Jessica

Jessica E. Barnes

Town Clerk

Riverdale Park

5008 Queensbury Road

Riverdale Park, MD 20737

www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/> 

301-927-6381

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150424/2f724eda/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 4-27-15 and 5-4-15 FINAL.pdf
Type: application/pdf
Size: 29475 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150424/2f724eda/attachment.pdf>


More information about the TownTalk mailing list