[RP TownTalk] Riverdale Park Station - Construction Update Notice Weeks of: April 27, 2015 and May 4, 2015
Jessica Barnes
jbarnes at riverdaleparkmd.gov
Fri Apr 24 17:03:01 UTC 2015
Riverdale Park Station
CONSTRUCTION UPDATE NOTICE
Weeks of: April 27, 2015 and May 4, 2015
What to Expect On-Site the Next Two Weeks:
During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market. They will also
continue removal and haul-off of excess soil and rubble.
The installation of the retaining wall along the Northern property line will
be completed by the end of April.
Lane Closures:
WSSC has commenced work on their replacement water main project in the Route
1 right-of-way. This work is not associated with the Riverdale Park Station
project.
Future Plans:
. Two week to two month look-ahead -
o Continue all of the above work but start an additional building to provide
new retail to the area.
o Utility installation work.
o Start construction of the pond at the northeast corner of the site.
o Start utility relocation for the construction of the CSX Crossing.
. Two to six month look-ahead -
o Start additional retail buildings.
o Start installation of a traffic signal at Van Buren St. & Rt.1.
. Six to twelve month look-ahead -
o Start interior fit-out of Whole Foods.
o Finish widening of Route 1.
o Opening of Gateway Park.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00am to 3:00pm.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150424/2f724eda/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 4-27-15 and 5-4-15 FINAL.pdf
Type: application/pdf
Size: 29475 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150424/2f724eda/attachment.pdf>
More information about the TownTalk
mailing list