[RP TownTalk] Riverdale Park Station Construction Update Notice for the Weeks of June 22 and 29, 2015
Sara Imhulse
simhulse at riverdaleparkmd.gov
Fri Jun 19 19:21:46 UTC 2015
CONSTRUCTION UPDATE NOTICE
Weeks of: June 22, 2015 and June 29, 2015
What to Expect On-Site the Next Two Weeks:
During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market and Building #3.
Underground utility work to install storm drains, sewers, and electric
conduits is proceeding in multiple areas on the site.
Lane Closures:
WSSC (using A&M Concrete Co.) has commenced work on their replacement water
main project in the Route 1 right-of-way. This work is not associated with
the Riverdale Park Station project. Work began on 6/15/15 installing the new
storm drain outfall pipe from the site to Wells Run. This installation will
move into Route 1 on 6/22/15 and take 3-4 weeks to complete. Pepco will be
installing a new pole on the west side of Rt.1. Pepco forces are currently
installing underground electric conduits across Route 1 to provide power to
the site.
Future Plans:
. Two week to two month look-ahead - o Continue all of the above work but
start an additional building to provide new retail to the area.
o Utility installation work.
o Start construction of the Whole Foods Market parking lot.
o Start construction of the pond at the northeast corner of the site.
o Start utility relocation for the construction of the CSX Crossing.
. Two to six month look-ahead - o Start additional retail buildings.
o Start installation of a traffic signal at Van Buren St. & Rt.1.
. Six to twelve month look-ahead - o Start interior fit-out of Whole Foods.
o Finish widening of Route 1.
o Opening of Gateway Park.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 7 p.m. However, work on the State highway will be restricted to
9:00am to 3:00pm.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150619/79fbee13/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 6-22-15 and 6-29-15 FINAL.pdf
Type: application/octet-stream
Size: 29950 bytes
Desc: not available
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20150619/79fbee13/attachment.obj>
More information about the TownTalk
mailing list