CONSTRUCTION UPDATE NOTICE
Weeks of: August 11, 2014 and August 18, 2014
What to Expect On-Site the Next Two Weeks:
During the next two weeks of work, the General Contractor, L.F. Jennings,
will continue construction of the Whole Foods Market and continue with site
utility work.
As well, they will continue clearing the site, continue removal and haul-off
of excess soil and trees, and continue rough grading operations on the site,
utilizing material haul-off. This will include work along the Route 1 buffer
area.
L.F. Jennings will also be performing installation of the water and sanitary
utilities in the SW corner of the site.
These activities will require heavy equipment accessing the site. Two of the
construction entrances are located along Route 1 located near both ends of
the project site and one entrance at Maryland Avenue.
Lane Closures:
There are no anticipated lane closures associated with this work.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7
a.m. and 5 p.m.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of
Capital Construction Consultants at 202-669-7157 or email at
rlockhart at ccci-dc.com.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info <http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20140811/496a4ad1/attachment.html>
More information about the TownTalk
mailing list