[RP TownTalk] Riverdale Park Station - Construction Update Notice for the Weeks of September 12 and 19, 2016
Jessica Barnes
jbarnes at riverdaleparkmd.gov
Mon Sep 12 12:47:52 UTC 2016
Riverdale Park Station
CONSTRUCTION UPDATE NOTICE
Weeks of: September 12, 2016 thru the week of September 19, 2016
What to Expect On-Site the Next Two Weeks:
The General Contractor, L.F. Jennings, will continue site construction in multiple areas on the site. Washington Gas Light (WGL), Verizon, Comcast, WSSC and Pepco will bring utility services to each new building. New road construction east of 46th Street to connect to Maryland Avenue is ongoing. The final asphalt topping course and striping of roads and parking areas will be completed before the end of the year on the western half of the site. The park adjacent to Route 1 (Gateway Park) is nearing completion. Bio-soil storm water retention devices are being installed throughout the site. The sidewalk and road work along Maryland Avenue, at the southeast corner of the site, has started. Fine grading for 119 townhome lots is ongoing so the townhome builder can start construction of these units this fall. Conduit and/or pipe installation for Washington Gas Light (WGL), Verizon, Comcast and Pepco services to each townhouse lot is ongoing. The first lots are being turned over to the townhouse developer in September. Construction of three new commercial buildings (#1, 2 & 4) is well underway. Tenant fitout work in Building #3, for spaces other than Whole Foods Market, has started.
CSX Crossing:
The bridge construction requires the closing of the former ERCO plant parking lot between the Rivertech Court cul-de-sac and Lafayette Avenue. This route has been used for years as a "short cut" from Lafayette Avenue to M-Square. This closure will continue until the new bridge is open - estimated to be in the third quarter of 2017. Initial activities will include installation of sediment controls, driving of piles and excavation for the bridge foundations. Pile driving will generate noise around that area. The pile installation will start early October and continue into early December.
Whole Foods Market:
Tenant fitout work inside Whole Foods Market has started. This construction is being managed by Whole Foods Market. They estimate that construction, stocking and employee training will take 9-10 months from the time construction work commences.
Hiker/Biker Trail:
The Hiker/Biker Trail has been deeded to MNCPPC's Department of Parks and Recreation who will manage and maintain the trail. They expect to open the trail for use by the public once they determine that site conditions are suitably safe from dangers associated with the immediately adjacent construction activities.
Work Hours:
Work activity will be taking place Monday - Sunday between the hours of 7 a.m. and 7 p.m. However, work on the State highway (Route 1) will be restricted to 9:00 a.m. to 3:00 p.m.
Contact Information:
For any construction related concerns, please contact Robert Lockhart of Capital Construction Consultants, Inc. at 202-669-7157 or email at rlockhart at ccci-dc.com<mailto:rlockhart at ccci-dc.com>.
For Stanley Martin townhome information, please contact Adam Carpenter at 301/636-6111 or email at CarpenterAQ at stanleymartin.com<mailto:CarpenterAQ at stanleymartin.com>.
Jessica
Jessica E. Barnes
Town Clerk
Riverdale Park
5008 Queensbury Road
Riverdale Park, MD 20737
www.riverdaleparkmd.info<http://www.riverdaleparkmd.info/>
301-927-6381
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20160912/56d4e2f3/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RP Project Construction Update Weeks of 9-12-16 thru week of 9-19-16 FINAL.pdf
Type: application/pdf
Size: 24772 bytes
Desc: RP Project Construction Update Weeks of 9-12-16 thru week of 9-19-16 FINAL.pdf
URL: <http://riverdale-park.org/pipermail/towntalk/attachments/20160912/56d4e2f3/attachment.pdf>
More information about the TownTalk
mailing list